Connection of Folegandros to the mainland electricity system via a new interconnection

6 outlets · 6 articles
Archive image: South Aegean
Archive image South Aegean · KF at English Wikipedia · Public domain · Wikimedia Commons
Who covers itEach circle is an outlet that covered the story, placed at its published political lean; the letters are its initials. 6 of the 6 outlets have a published lean.
Far leftFar LLeftLeftCentre-leftC-LCentreCtrCentre-rightC-RRightRightFar rightFar R
Which outlet each circle is
  • Politic.gr Centre
  • Newsbeast Centre-right
  • liberal.gr Centre-right
  • Mononews Centre-right
  • Powergame Centre-right
  • Ta Nea Centre-right

What is happening

What the sources report

Folegandros is now supplied with electricity from the mainland electricity system, via Naxos and Santorini. Ta Nea

The development confirms the operation of the undersea cable system installed by ADMIE as part of the interconnection of the southern Cyclades, a project with a budget of EUR 385.7 million. liberal.gr

The cable of the Santorini–Folegandros section is 60 km long, operates at 150 kV, and was laid at a maximum depth of 340 m. Ta Nea

Earlier, in June, the construction of the interconnection, which includes Santorini, Folegandros, Milos and Serifos, had been completed. Politic.gr

ADMIE's chairman and CEO, Manos Manousakis, stated that Folegandros is now part of the interconnected electricity system. Politic.gr

Where they differ

The media do not differ on the basic facts.

AI-generated summary (Claude) based on 3 articles. It may contain errors; please check the sources.

Spotted an error?

The editor reads it. The email is deleted as soon as the report is closed.

How each side headlined it

Each outlet's first headline, by its published political lean. The method

All articles by time (6)

When each outlet covered it

First report 19 October at 14:41, latest 20 October at 14:50. Within the first hour: 5 of 6 outlets. Each column: 2 hours.